Cameroon

Construction, Rehabilitation and Extension of Cameroonian Water Supply Systems (Phase 4 - T4)

(2013-04-01 - 2015-01-30)

The project aims to rehabilitate and build water supply systems within the whole country. The contract is divided into 5 phases:

 

Bélabo

Rehabilitation work including:

  •  - Rehabilitation of the water treatment plant (25 m³/h).
  •  - Rehabilitation of raw and treated water pumping systems.

 

Bikok

Rehabilitation work including:

  •  - Replacement of the Compact Treatment Plant (12 m³/h).
  •  - Rehabilitation of the raw water pumping systems (river intake).

 

Buea

Rehabilitation work including:

  •  - Replacement of an old asbestos-cement pipe with a new HDPE pipe between the P2 Mosel Spring pumping station and the P3 reservoir (HDPE OD 315 - SDR17, 2 km)

 

Foumbot

Rehabilitation work including:

  •  - Rehabilitation of the water treatment plant (100 m³/h).
  •  - Rehabilitation of raw and treated water pumping systems.

 

Kaélé

Rehabilitation work including:

  •  - Construction of 2 boreholes (50 m³/h and 20 m³/h).
  •  - Construction and installation of 1 chlorination unit.

 

Mbouda

Rehabilitation work including:

  •  - Rehabilitation of 1,000m³ concrete reservoir.
  •  - Replacing 4 km of the raw water transfer pipe.
  •  - Rehabilitation of the water treatment plant (110 m³/h).

 

Meyomessala

Rehabilitation work including:

  •  - Rehabilitation and extension of a treatment station (40 m³/h).
  •  - Rehabilitation of raw and treated water pumping systems.

 

Mfou

Rehabilitation work including:

  • - Rehabilitation of water treatment plant (30 m³/h).
  • - Rehabilitation of raw and treated water pumping systems.

 

Nanga Eboko

Rehabilitation work including:

  •  - Rehabilitation of a treatment station (50 m³/h).
  •  - Rehabilitation of raw and treated water pumping systems.

 

Yaoundé

  •  - Installation of a raw water pump (1,458 m³/h at 41.5 m, 250 kW – 6 kV)
  •  - Installation of a treated water pump (1,389 m³/h at 121m, 650 kW – 6 kV)
  •  - Installation of the electrical cells and of the remote management system.