Cameroon

Construction, Rehabilitation and Extension of Cameroonian Water Supply Systems (Phase 5 - T5)

(2016-03-01 - 2017-11-30)

The project aims to rehabilitate and build water supply systems within the whole country. The contract is divided into 5 phases:

 

Akonolinga

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant (88 m³/h).
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.
  •  - Reinforcement of the electrical line MV/LV and installation of a 100 kVA transformer at the treatment plant.

 

Ambam

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant (22 m³/h).
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.

 

Batouri

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant and extension of its capacity (110 m³/h).
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.

 

Campo

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Reinstallation of the treatment units by a new and more efficient containerized unit (20 m³/h).
  •  - Construction of a technical building.
  •  - Construction of a treated water slab in reinforced concrete.
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.
  •  - Reinforcement of the electrical line MV/LV and installation of a 100 kVA transformer at the treatment plant.

 

Evodoula

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant and extension of its capacity (25 m³/h).
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Reinstallation of a part of the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.
  •  - Reinforcement of the electrical line MV/LV and installation of a 100 kVA transformer at the treatment plant.

 

Monatélé

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant (30 m³/h).
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.
  •  - Reinforcement of the electrical line MV/LV to the treatment plant.

 

Okola

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant and extension of its capacity (25 m³/h).
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.
  •  - Reinforcement of the electrical line MV/LV and installation of a 100 kVA transformer at the treatment plant.

 

Sa’a

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant (22 m³/h).
  •  - Rehabilitation of the treated water pump and reinstallation of the hydro-mechanical equipment on the treated water main towards the water storage reservoir.
  •  - Rehabilitation of the reservoir.
  •  - Reinforcement of the electrical line MV/LV to the treatment plant.

 

Yokadouma

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant and extension of its capacity (80 m³/h).
  •  - Rehabilitation of the treated water pump and reinstallation of the hydro-mechanical equipment on the treated water main towards the water storage reservoir.
  •  - Rehabilitation of the reservoir.
  •  - Reinforcement of the electrical line MV/LV and installation of a 100 kVA transformer at the treatment plant.

 

Zoetele

Rehabilitation works including:

  •  - Rehabilitation of the intake and the raw water pumping station.
  •  - Rehabilitation of the treatment plant (25 m³/h).
  •  - Rehabilitation of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank.
  •  - Rehabilitation of the elevated tank.
  •  - Reinforcement of the electrical line MV/LV and installation of a 100 kVA transformer at the treatment plant.
  •  - Reinstallation of the damaged part of the distribution main.