Cameroon

Densification of Drinking Water Supply Networks (C1)

(2015-08-03 - 2017-02-28)

The Project consists of the laying of 200 km of tertiary distribution networks, including the installation of valves, washouts and air chamber valves in 11 cities across Cameroon.

It also includes the construction of the Maroua University Drinking Water Supply System as well as the extension and densification of the drinking water supply systems in Banyo and Garoua cities.

 

Bafoussam

Densification of the distribution network:

  •  - Laying of 17 km of HDPE OD 63, OD 90, OD 110 and OD 160 pipes;
  •  - Procurement and laying of section valves.
  •  - Construction of 1 air valve chamber.

 

Banyo

Rehabilitation works including:

  •  - Construction of a new raw water intake.
  •  - Rehabilitation of the treatment plant and extension of its capacity (80 m³/h).
  •  - Rehabilitation of the reservoir.
  •  - Connection to the power grid.

 

Bélabo

Densification of the distribution network:

  •  - Laying of 7.25 km of HDPE OD 63 and OD 90 pipes.
  •  - Procurement and installation of section valves.
  •  - Installation of 7 washouts.
  •  - Construction of 2 air valve chambers.

 

Buea

Densification of the distribution network:

  •  - Laying of HDPE OD 63, OD 90 and OD 110 pipes.
  •  - Procurement and installation of section valves.
  •  - Installation of 6 washouts.
  •  - Construction of 4 air valve chambers.

 

Douala

Densification of the distribution network including:

  •  - Laying of 72 km of HDPE OD 63, OD 90, OD 110 and OD 160 pipes.
  •  - Procurement and installation of section valves.
  •  - Installation of 55 washouts.
  •  - Construction of 35 air valve chambers.

 

Garoua

Densification of the distribution network including:

  •  - Laying of 20km of HDPE OD 63, OD 90, OD 110 and OD 250 pipes.
  •  - Procurement and installation of section valves.
  •  - Construction of 1 meter chamber.
  •  - Installation of 11 washouts.
  •  - Construction of 1 borehole (100 m³/h).
  •  - Procurement and installation of a chlorination unit.

 

Limbe

Densification of the distribution network:

  •  - Laying 7.7 km of HDPE OD 63, OD 90 and OD 110 pipes.
  •  - Procurement and installation of section valves.
  •  - Installation of 3 washouts.
  •  - Construction of 2 air valve chambers.

 

Maroua Extension

Densification of the distribution network:

  •  - Laying of 9.6 km of HDPE OD 63, OD 90 and OD 110 pipes.
  •  - Procurement and installation of section valves.
  •  - Construction of 1 air valve chamber.

 

Maroua University

New Centre including:

  •  - Laying 3 km of HDPE OD 63, OD 90 and OD 160 pipes.
  •  - Procurement and installation of section valves.
  •  - Construction of a borehole (50 m³/h).
  •  - Procurement and installation of a chlorination unit.
  •  - Construction of an elevated tank in reinforced concrete (300 m³).

 

Nkongsamba

Densification of the distribution network:

  •  - Laying of 12 km of HDPE OD 63 and OD 90 pipes.
  •  - Procurement and installation of section valves.
  •  - Installation of 2 washouts.
  •  - Construction of 1 air valve chamber.

 

Yaounde

Densification of the distribution network:

  •  - Laying of 40.6 km of HDPE OD 63, OD 90, OD 110 and OD 160 pipes.
  •  - Procurement and installation of section valves.
  •  - Installation of 16 washouts.
  •  - Construction of 9 air valve chambers.