- Construction of an elevated 200 m³ reservoir
- 3 boreholes (total flow 53 m³)
- Supply network (3.5km)
- Distribution network (11.6 km)
- 14 standpipes
- Ground-level construction of a 1,000 m³ reservoir
- Installation of a compact treatment unit (CTU) with a capacity of 447 m³/d;
- Rehabilitation of the Soudou network (28 m³)
- Water supply network 16.6 km
- Distribution network (6.3 km)
- 31 standpipes